Major Capital Projects Dashboard

Major Capital Projects Dashboard

Progress Report to reflect project statuses for the 2nd quarter of 2020.

This dashboard displays statuses of all major projects to include new/replacement schools, systemic replacements and interior renovations with a budget in excess of $10M.

 Orange symbol indicates a project may have budget or schedule concerns--there are issues that bear monitoring.

 Red symbol indicates a project has significant budget and/or schedule concerns--there are issues to be addressed.

 Green symbol indicates the project is on schedule and on budget--there are no pending issues of concern.


How To Navigate the Capital Projects Dashboard

Project/School/Facility Status Budget Planning/Design Start Construction Start Phase & Percentage General Overview Status Project Team Notes Project ID Photos
New Adelphi Area MS $80,000,000 2018 October 2019 Planning Phase 80% A new school with 157,900 sf, including cooperative use space for 1,200 students. Major project included in Alternative Construction Financing (ACF) package 1. ACF Request for Proposal being finalized. TBD
Andrew Jackson Academy HVAC $17,641,000 2016 August 2020 Construction Phase 0% Systemic Renovation: Replace 1971 HVAC equipment including one (1) chiller, 14 air handling units, heating and cooling piping, and the controls system, replace one (1) 1996 cooling tower, and replace two (2) 2000 steam boilers with hot water boilers. Contract award to Construction Management consultant. Architect: Kibart; Construction Manager: TBD; PGCPS Project Manager: Henry Lewis
Bowie-Belair High Annex $23,417,000 2014 December 2019 Construction Phase 0% Limited renovation and improvements to the existing special education program. Includes (5) major systemic projects in addition to educational program enhancements. Selection and contract award to Construction Management consultant. Architect: DLR Group; Contractor: Hess Construction; PGCPS Project Manager: Hiwot Haileselassie
Central HS HVAC $20,218,000 2016 March 2020 Construction Phase 0% Systemic Renovation: Replace the entire 1982 heating and ventilating system with a complete heating, ventilating and air conditioning system, including boilers, chiller, rooftop units, air handling units, terminal units, piping, and controls. Await receipt of building permits and IAC approvals. Architect: Gipe Associates, Inc.; Construction Manager: Oak Contracting LLC; PGCPS Project Manager: Nadine Belizaire
Cherokee Lane ES $34,000,000 2019 February 2020 Design Phase 95% Replacement of a new school with 95,000 sf on a new site, for 846 SRC. Construction documents submitted to DGS for final approval November 2019. Architect: Gilbert Architect, Inc.; Construction Manager: Whiting & Turner Contracting; PGCPS Project Manager: Joseph Howell
Cool Spring Annex-Judy Hoyer Ctr. $ 2019 January 2020 Planning Phase 50% Renovation, addition and conversion of a 58,000 SF annex building with existing office spaces into additional 560 student elementary school space. Development of the Request for Proposal to solicit Architectural/Engineering services. PGCPS Contact: Ronald Kauffman, Planner II
New Glenridge Area MS $80,000,000 2017 April 2020 Design Phase 95% Construction of a new 160,900 sf and 1,180 SRC middle school in the Glenridge area. Construction documents submitted to DGS August 2019. Third party review started October 9, 2019. Property exchange Term Sheet signed with M-NCPPC. Final Memorandum of Understanding in progress. Architect: Grimm and Parker; Construction Manager: MCN Build; PGCPS Project Manager: Hiwot Haileselassie Photos
High Point HS $189,000,000 2018 January 2020 Planning Phase 95% Modernization/additions to the existing 2081 seat (SRC) high school to create a 2500 seat high school on the same site. Review responses to the Architectural/Engineering RFP. Architect: TBD; Contractor or Construction Manager: TBD; PGCPS Planner: Joseph Wolf
International HS @ Langley Park $34,000,000 2016 September 2020 Design Phase 35% New school 58,000 sf, including cooperative use space, for 400 SRC. End-users, community members and the Project Planning Committee have been meeting with the DCP team and Architect to develop the design for this new high school. The Schematic Design was submitted to MSDE for formal approval at the end of August 2018. Initial cost estimates were high and the architects were asked to revise the plans. Architect: DLR Group; Contractor or Construction Manager: TBD; PGCPS Project Manager: Hiwot Haileselassie
New Northern Adelphi Area HS $ 2019 January 2020 Planning Phase 35% Construction of a new 369,806 SF and 2,600 student high school in the Adelphi area. Reviewing responses to the Architectural/Engineering RFP. PGCPS Contact: John Wooden
Stephen Decatur MS SEI $10,501,000 2014 June 2020 Construction Phase 0% Special Education Inclusion Renovation: Renovate 11,240 net sq. ft. (17,000 GSF) in the southeast corner of the building for the CRI/Regional Program and an added space for the therapy pool to serve the regional students in the area. Finalize and release "Invitation For Bid" to solicit general contracting services. Architect: CRA Architects; Contractor: TBD; PGCPS Project Manager: Henry Lewis
Suitland HS $219,000,000 2017 January 2020 Planning Phase 95% Full Renovation and/or Replacement of the existing 344,875 SF Suitland High School Campus End-users, community members and the Project Planning Committee (PPC) will start meeting again with the DCP team and Architect to develop the design for this high school campus. Feasibility Study: Grimm and Parker; Design Architect: TBD; Contractor or Construction Manager: TBD; PGCPS Contact: Ronald Kauffman
William Schmidt Outdoor Ed. Center $32,000,000 2016 September 2020 Design Phase 50% Modernization of and upgrades to the Center, to include construction of a second residential village, central dining hall, and environmental learning center as well as modernization of the Village I complex and modernization/adaptive reuse of the Orme Building. End-users, community members and the Project Planning Committee have been meeting with the DCP team and Architect to develop the design for this center. Architect: Quinn Evans; Contractor or Construction Manager: TBD; PGCPS Contact: Joseph Wolf
William Wirt MS $85,000,000 2017 April 2020 Design Phase 95% Demolition of the existing 106,318 SF facility built in 1964 with a State Rated Capacity (SRC) of 850 students and replacement with a new 170,900 SF facility with a SRC of 1,200 students at the same site. End-users, community members and the Project Planning Committee met with the DCP team and Architect to develop the design for this replacement school. Architect: Crabtree, Rohrbaugh & Associates; Contractor or Construction Manager: TBD; PGCPS Project Manager: Henry Lewis Photos