Major Capital Projects Dashboard

Major Capital Projects Dashboard

Progress Report to reflect project statuses for the 2nd quarter of 2024.

This dashboard displays the statuses of all major projects including new/replacement schools, systemic replacements, and interior renovations with a budget of over $10M.

 Orange symbol indicates a project may have budget or schedule concerns--there are issues that bear monitoring.

 Red symbol indicates a project has significant budget and/or schedule concerns--there are issues to be addressed.

 Green symbol indicates the project is on schedule and on budget--there are no pending issues of concern.

How To Navigate the Capital Projects Dashboard

To navigate
     Clicking the project name will direct you to its associated project.
Using the table
     Sorting
          Click the column headers to toggle results alphabetically (ascending & descending.)
     Columns
          Stack: (Default)The Stack view stacks the table headers to a two column layout with headers on the left when viewing on a mobile device.
          Swipe: Allows the user to use the swipe gesture (or use the left and right buttons) to navigate the columns.
          Toggle: The Column Toggle view allows the user to select which columns they want to be visible.

Project/School/Facility Status Budget Planning/Design Start Construction Start Phase & Percentage General Overview Status Project Team Notes Project ID Photos
Andrew Jackson Academy HVAC $17,641,000 2016 September 2020 Construction Phase 99% Systemic Renovation: Replace 1971 HVAC equipment including one (1) chiller, 14 air handling units, heating and cooling piping, and the controls system, replace one (1) 1996 cooling tower, and replace two (2) 2000 steam boilers with hot water boilers. Project has reached substantial completion. Architect: Kibart; Construction Manager: Keller Construction Management; PGCPS Project Manager: Henry Lewis PSC 16.197.18 SR Priority 29
Bowie-Belair High Annex $25,865,000 2014 December 2019 Construction Phase 97% Limited renovation and improvements to the existing special education program. Includes (5) major systemic projects in addition to educational program enhancements. All phases for classrooms, offices and admin areas have received temporary occupancy. Architect: DLR Group; Contractor: Hess Construction; PGCPS Project Manager: Hiwot Haileselassie PSC 16.041.19 C, Priority # 3
Central HS HVAC $20,218,000 2016 March 2020 Construction Phase 98% Systemic Renovation: Replace the entire 1982 heating and ventilating system with a complete heating, ventilating and air conditioning system, including boilers, chiller, rooftop units, air handling units, terminal units, piping, and controls. Final close out items in progress: final inspections and training. Architect: Gipe Associates, Inc.; Construction Manager: Oak Contracting LLC; PGCPS Project Manager: Anoop Gupta PSC 16.010.18 SR, Priority #28
Charles Herbert Flowers HS HVAC Renovation $11,168,241 2019 June 2022 Design Phase 0% Replace the 1999 HVAC System Design Development documentation submitted. Architect to complete Construction Documents. PGCPS Project Manager, Sunday Owolabi 16.174.21 SR, PRI# 10
Cherokee Lane ES $34,000,000 2019 April 2020 Construction Phase 99% Replacement of a new school with 95,000 sf on a new site, for 846 SRC. Closing out punch-list items Close-out document review by PM & Design team. Obtain DPIE final acceptance of the site for Permanent U&O Obtain the balance of FF&E Items Architect: Gilbert Architect, Inc.; Construction Manager: Whiting & Turner Contracting; PGCPS Project Manager: Joseph Howell PSC 16.267.20 C, Priority #11 Photos
Cool Spring Annex-Judy Hoyer Ctr. $85,221,055 2019 January 2020 Planning Phase 50% Renovation, addition and conversion of a 58,000 SF annex building with existing office spaces into additional 560 student elementary school space. Current Status: Design Architect was awarded to Gilbert Architects Inc on October 23, 2022. A Notice of Award (NOA) was sent to the Architect. Design of the facility is scheduled to commence. Upcoming Activities: End-users, community members and the Project Planning Committee (PPC) will be meeting with the DCP team and Architect to develop the design for this new elementary school space. PGCPS Contact: Sunday Owolabi, Project Manager
Dwight Eisenhower Middle School HVAC Renovation $12,063,600 2022 July 2022 Design Phase 49% HVAC & Building Envelope / Replace the 1969-1974 central controls system, HVAC piping, all ten (10) AHUs, 45 finned tube radiators, four (4) self-contained unit ventilators, 17 floor mounted fan coil units, two (2) ceiling mounted AHUs, chiller Windows and Doors component of the project is complete. HVAC Design continues. Evaluations complete. Architect/Engineer: Global Engineering SolutionContractor: The Matthews Group (TMG)PGCPS Project Manager: Anoop Gupta 16.008.19 SR, PRI# 12
New Glenridge Area MS $80,000,000 2017 December 2021 Construction Phase 68% Construction of a new 160,900 SF and 1,180 SRC middle school in the Glenridge area to alleviate current overcrowding in neighboring schools & meet the demands of projected enrollment. Moving of the Imani Temple sanitary line was completed. A temporary screen and fence were installed. Sediment basin A was completed. Boilers, chiller, and partial AHUs were delivered. The release of the switchgear was completed. Architect: Grimm and Parker; Construction Manager: MCN Build; PGCPS Project Manager: Hiwot Haileselassie PSC 16.265.20 C, Priority #4 Photos
High Point HS $189,000,000 2018 January 2020 Planning Phase 95% Modernization/additions to the existing 2081 seat (SRC) high school with 318,376 SF to create a 2600 student high school with 423,000 SF on the same site. End-users, community members and the Project Planning Committee will be meeting with DCP team and Architect to develop the design for this high school. Architect: TBD; Contractor or Construction Manager: TBD; PGCPS Contact: TBD
International HS @ Langley Park $34,000,000 2016 September 2020 Design Phase 35% New school 58,000 sf, including cooperative use space, for 400 SRC. Department of Capital Programs is currently reviewing the drawings and providing comments back to the Architect for corrections. Construction Document phase completion anticipated Fall 2022. Architect: DLR Group; Contractor or Construction Manager: TBD; PGCPS Project Manager: Hiwot Haileselassie
James Madison Middle School HVAC Replacement $10,421,000 2020 June 2022 Construction Phase 32% Replacement of HVAC piping system, chiller, cooling tower, four (4) air handling units, 96 mixing boxes, twenty (20) finned tube radiators, fifteen (15) convectors, and controls. Exterior Windows, Doors and Storefront work in progress. Contractor: Protec Construction Inc.; PGCPS Project Manager: Anoop Gupta 16.114.20 SR, PRI# 12
New Northern Adelphi Area HS $ 2020 July 2022 Planning Phase 75% Construction of a new 369,806 SF and 2,600 student high school in the Adelphi area. Current Status: Continue scheduled Project Planning Committee (PPC) meetings. Upcoming Activities: Completion of Schematic Design (SD) phase. Architect/Engineer: Gilbert Architects, Inc.; Contractor: TBD; PGCPS Contact: Joseph Howell
Robert Goddard Montessori HVAC Renovation $16,047,000 2016 June 2020 Construction Phase 95% Systemic Renovation: Replace / upgrade the 1964 106,701 SF school building and 1966 26,930 SF addition mechanical system, composed of two gas fired steam boilers and one chiller. Projected completion anticipated for Spring 2022. Architect: Gannett Fleming, Inc.; Contractor: Fresh Air Concepts, LLC; PGCPS Contact: Sean Nickols, Project Manager II 16.181.18 SR, PRI# 46
Stephen Decatur MS SEI $15,105,800 2014 September 2020 Construction Phase 98% Special Education Inclusion Renovation: Renovate 11,240 net sq. ft. (17,000 GSF) in the southeast corner of the building for the CRI/Regional Program and an added space for the therapy pool to serve the regional students in the area. Electrical power switchover by PEPCO. Completion of fire alarm. Architect: CRA Architects; Contractor: Keller Brothers, Inc.; PGCPS Project Manager: Henry Lewis PSC 16.143.16 C, Priority #2
Suitland HS $335,000,000 2017 January 2022 Construction Phase 10% Full Renovation and/or Replacement of the existing 344,875 SF Suitland High School Campus A fine grade permit is expected. Building pad and foundation installation will be completed. Mechanical, electrical, and plumbing work will be completed to support foundation work. Masonry work for the foundation and stair towers will be completed. Feasibility Study: Grimm and Parker; Design Architect: Cox Graae + Spack Architects; Construction Manager: Tuner-Corenic Construction Joint Venture; PGCPS Contact: Sean Nickols
William Schmidt Outdoor Ed. Center $32,000,000 2016 March 2021 Design Phase 75% Modernization of and upgrades to the Center, to include construction of a second residential village, central dining hall, and environmental learning center as well as modernization of the Village I complex and modernization/adaptive reuse of the Orme Building. Contractor bids were received. The project was awarded to Oak Contracting, LLC. Construction is scheduled to start in Winter 2024. Architect: Quinn Evans; Contractor or Construction Manager: TBD; PGCPS Contact: Chuck Floeck PSC 16.199.18 C, Priority #5
William Wirt MS $85,000,000 2017 April 2021 Construction Phase 90% Demolition of the existing 106,318 SF facility built in 1964 with a State Rated Capacity (SRC) of 850 students and replacement with a new 170,900 SF facility with a SRC of 1,200 students at the same site. Structural steel and roofing installation were completed. The switchgear was installed and is waiting on permanent power by Pepco. In-wall electrical and plumbing rough-ins and sprinkler rough-ins were completed. Exterior Veneer and interior stone veneer were completed. Installation of rooftop equipment screens was completed. Architect: Crabtree, Rohrbaugh & Associates; Contractor or Construction Manager: TBD; PGCPS Project Manager: Henry Lewis PSC 16.183.20 C, Priority #2 Photos